Project 27: Early January Winter Update 2024
With the start of the new year and the frames sheeted over, to protect them from the elements, the team has started to move forwards on two fronts…
With the start of the new year and the frames sheeted over, to protect them from the elements, the team has started to move forwards on two fronts…
It has been a busy winter working on 27 with the rear drag box & buffer beam complete and riveted in place for the close of the year. The cylinder block has also been split ready for final machining & the second wheel set has also entered the works over winter…
With the 150th anniversary of Stroudley’s famed “Terriers” fast approaching in 2022 an in-depth evaluation has been started on first of the class Fenchurch, by the Bluebell Railway’s Locomotive Works, with a view to returning her to steam for the anniversary…
We have just received back from Statfold barn our refurbished valve rods which where sent away for metal spraying and re machining of the working surfaces back to original finish size! The finish is absolutely superb and will complement the new block when they come to be fitted…
To the casual observer maybe not much has changed but with over 400 holes previously drilled we have slowly been setting up the frames over the summer carefully aligning the various frame plates, reaming through and countersinking the various holes…
Over the first week of July we had a small team of volunteers from Network Rail spending the week undertaking various tasks helping with the ongoing restoration of No 27 Primrose as well as helping with preventative maintenance & remedial display presentation…
Fenchurch over the pit ready for its deep clean by NR volunteers pending its next overhaul…
As a small group, we rely on fundraising to keep achieving our goal of seeing the Bluebell Railways smaller fleet of engines operational. So get on board with us today no matter how large or small the contribution.