Project 27

Project 27: Early January Winter Update 2024
With the start of the new year and the frames sheeted over the team has started to move forwards on two fronts.
Firstly, they have started working on the RHS side tank. The tank has been moved around and placed on support trestles to allow for the careful cutting out of the bottom plate work. This will enable the team to assess the extent of repair work needed. Additionally, they have removed various brackets and lamp irons from the old running plates, which will be cleaned up and painted before being fitted to the new platework….

Project 27: Early January Winter Update 2024
With the start of the new year and the frames sheeted over the team has started to move forwards on

Project 27: Autumn & Winter Update 2022
Following on from the beginning of the year the team has slowly been working towards finishing off the final construction

Fenchurch 150: Overhaul Update Part 1 August 2022
Andy Kelly’s photos record the passing of the out-of-frames steam test, and bacon being fried in the tradition manner for celebratory bacon brioches. During the Terrier 150 event, the incomplete ‘Fenchurch’ was displayed as best as was possible in the circumstances alongside ‘Stepney’, as seen in Owen Hayward’s photo from 30 July…

Fenchurch 150: Overhaul Update 21st July 2022
Fenchurch’s boiler has passed its hydraulic test, and boiler fittings are being overhauled and re-attached, as seen in Andy Kelly’s photos below. It is hoped that the loco will be assembled ready for display alongside ‘Stepney’ over the Terrier 150 weekend coming up on 29-31 July…

Fenchurch 150: Overhaul Update Part 2 June 2022
A second update for June see’s the majority of the boiler work for Fenchurch’s boiler almost complete with only a few additional tasks to be finished off before the boiler is ready for a hydraulic & initial steam test. The opportunity was taken at this stage to make a trial fitment of the boiler…

Fenchurch 150: Overhaul Update Part 1 August 2022
Andy Kelly’s photos record the passing of the out-of-frames steam test, and bacon being fried in the tradition manner for celebratory bacon brioches. During the Terrier 150 event, the incomplete ‘Fenchurch’ was displayed as best as was possible in the circumstances alongside ‘Stepney’, as seen in Owen Hayward’s photo from 30 July…

Fenchurch 150: Overhaul Update 21st July 2022
Fenchurch’s boiler has passed its hydraulic test, and boiler fittings are being overhauled and re-attached, as seen in Andy Kelly’s photos below. It is hoped that the loco will be assembled ready for display alongside ‘Stepney’ over the Terrier 150 weekend coming up on 29-31 July…

Fenchurch 150: Overhaul Update Part 2 June 2022
A second update for June see’s the majority of the boiler work for Fenchurch’s boiler almost complete with only a few additional tasks to be finished off before the boiler is ready for a hydraulic & initial steam test. The opportunity was taken at this stage to make a trial fitment of the boiler…