Engineering Update 1st Quarter 2022
2022 a new year and a fresh start on project 27 following almost 2 years of lockdowns, restrictions & towards the tail end of 2021 the team getting back upto speed with where we left off. Work has mainly concentrated on progressing on with the overhaul of some of the various components currently taking up space in the villas so that we can either hang them back on the frames or put them into storage & out of the way.
Outside work on the frames has concentrated with the fettling of the front buffer beam angle rivet heads to allow the front counterweight to be temporarily fitted. The counterweight fitment being necessary not only to hold the front of the frames square, whilst the cylinder block is still to be fitted, but also to allow us subsequently make a start at setting up the front end & side valences.