Project 27: Early January Winter Update 2024
With the start of the new year and the frames sheeted over, to protect them from the elements, the team has started to move forwards on two fronts…
With the start of the new year and the frames sheeted over, to protect them from the elements, the team has started to move forwards on two fronts…
With a week’s annual leave booked some of the team spent the week making a start at riveting the frames! Both of the two frame stretchers have now been riveted home as well as the six running plate supports with the front two needing to be in place prior to the new cylinder block being fitted! Attention was then turned to making a start at fitting up the rear buffer beam and drag box…
It’s been a little while since our last engineering update but despite the weather we have slowly been moving forwards on many fronts! Work has focused on setting up the frames and getting them square ready for riveting! Also whilst the weather has been against us we have been busy making a start on re-furbishing various parts of the motion cleaning, inspecting & re-machining where necessary. Off site the cylinder block is progressing well…
As a small group, we rely on fundraising to keep achieving our goal of seeing the Bluebell Railways smaller fleet of engines operational. So get on board with us today no matter how large or small the contribution.