Featured News

Project 27

Project 27: Early January Winter Update 2024

With the start of the new year and the frames sheeted over the team has started to move forwards on two fronts.
Firstly, they have started working on the RHS side tank. The tank has been moved around and placed on support trestles to allow for the careful cutting out of the bottom plate work. This will enable the team to assess the extent of repair work needed. Additionally, they have removed various brackets and lamp irons from the old running plates, which will be cleaned up and painted before being fitted to the new platework….

Read More »

Fenchurch 150: Overhaul Update April 2022

With all the major parts of the firebox & boiler having been repaired or replaced the inner firebox was lowered into position and the firehole door ring & foundations ring have been finally aligned and fitted into position. This has enabled work to now concentrate on riveting in & staying the new firebox…

Discover More »

Engineering Update 1st Quarter 2022

2022 a new year and a fresh start on project 27 following almost 2 years of lockdowns, restrictions & towards the tail end of 2021 the team getting back upto speed with where we left off. Work has mainly concentrated on progressing on with the overhaul of some of the various components currently taking up space in the villas so that we can either hang them back on the frames or put them into storage…

Discover More »

Fenchurch 150: Overhaul Update March 2022

With the work now completed for the fitment of the new throatplate, firebox outer wrapper & repair section to the backhead pressing the boiler work continues on a pace towards the fitment of the new inner firebox. New pads & washout plug bosses have been welded onto the new outer wrapper…

Discover More »

Fenchurch 150: Overhaul Update April 2022

With all the major parts of the firebox & boiler having been repaired or replaced the inner firebox was lowered into position and the firehole door ring & foundations ring have been finally aligned and fitted into position. This has enabled work to now concentrate on riveting in & staying the new firebox…

Discover More »

Engineering Update 1st Quarter 2022

2022 a new year and a fresh start on project 27 following almost 2 years of lockdowns, restrictions & towards the tail end of 2021 the team getting back upto speed with where we left off. Work has mainly concentrated on progressing on with the overhaul of some of the various components currently taking up space in the villas so that we can either hang them back on the frames or put them into storage…

Discover More »

Fenchurch 150: Overhaul Update March 2022

With the work now completed for the fitment of the new throatplate, firebox outer wrapper & repair section to the backhead pressing the boiler work continues on a pace towards the fitment of the new inner firebox. New pads & washout plug bosses have been welded onto the new outer wrapper…

Discover More »