Project 27

Project 27: Summer Update 2022

Following on from the start of the year and with the side valances previously set in place after the temporary fitment of the front end for alignment the four valence end plate wings where finally welded into place. With this work completed a start could be made at finishing off the final riveting to the rear end of the frames as well as the front end, once the counterweights had been removed and in doing…

Read More »
Project 27

Engineering Update 1st Quarter 2022

2022 a new year and a fresh start on project 27 following almost 2 years of lockdowns, restrictions & towards the tail end of 2021 the team getting back upto speed with where we left off. Work has mainly concentrated on progressing on with the overhaul of some of the various components currently taking up space in the villas so that we can either hang them back on the frames or put them into storage…

Read More »
Project 27

Mini December Update 2021

With Autumn upon us & restrictions further lifted the team has progressed on with the painting of the frames with the first top coat black being applied to the frame plates before the weather inevitably turns too cold to make any further progress…

Read More »
Project 27

Autumn Engineering Update 2021

With Autumn upon us & restrictions further lifted the team has progressed on with the painting of the frames with the first top coat black being applied to the frame plates before the weather inevitably turns too cold to make any further progress…

Read More »